• Establishment of construction site offices in accordance with the contract and specification basis for operation in close proximity to the jobsite,
  • The contractor shall provide the site access, temporary structures, facilities, storage areas, service roads, parking areas and their related functions (including the site access, temporary structures, facilities, storage areas, parking areas and their related functions) of the contractors to ensure that the contractors prepare the site layout plans and establish the site facilities Controls the suitability of the connection in terms of permanent work, as far as possible)
  • By taking the plankot of the production area, all the settlements are checked according to the zoning situation and the state plan,
  • Where necessary, the identification of material quarries and excavation casting areas,
  • Coordinating the workforce in coordination with the Contractor in accordance with the work program, making the necessary arrangements for efficient use of labor capacity,
  • Ensuring that the technical personnel committed by the Contractor are at work and ensuring that inadequate personnel change when necessary;
  • Arranging the contractor site book, making follow-up and day-to-day manufacturing, providing daily processing of general materials, employee team and equipment situation,
  • The supervisor from the contractor supervises the implementation of the program related to job security (this includes the training of workers in the periodic meetings and programs and occupational safety) to ensure that the occupational health practitioner is available.
  • Especially in critical phases of the construction (basic application, concrete casting, etc.), it is very important to be careful in the inspection and to make the necessary measurements,
  • All materials to be used in contractor construction are taken into consideration; If no material is manufactured, payment of progress payment shall not be made and it shall be ensured that it is removed from the shipment immediately.
  • To make the final checks of the application projects before the start of the production and to ensure that the production is carried out in accordance with the project, building technique and the code of conduct,
  • To arrange monthly progress reports according to work items completed during the month; To ensure that the formate and the necessary minutes, documents and pictures determined by the address are in progress,
  • Safety orientation is to ensure that the information plates and instructions are of the same standard throughout the site and that they are placed in the appropriate places and that they are kept in check to ensure continuity in this regard,
  • To ensure that the temporary premises of the board of directors (dormitories, dining hall, etc.) are clean, well-maintained and hygienic,
  • Checking whether the contractor has the necessary machinery and equipment to run the work in time and correctly according to the work schedule and checking the adequacy of these capacities and if necessary by warning the Contractor to do this with technical suggestions,
  • To control the materials entering and leaving the site, ensuring that the materials are available for the execution of the works,
  • To make all kinds of tests related to machine installation and electrical installation. To ensure that approvals are obtained from the necessary institutions and organizations,
  • When necessary, all kinds of quantities, attachments, relays, minutes, new price analysis and so on. Preparing and signing documents,
  • To check the test results of all materials subjected to the test and to ensure that defective and defective materials are removed from the site.
  • To continuously monitor the contractors’ work safety measures and to ensure maximum safety in the field of work safety so as to reduce all kinds of work accidents that may occur in the construction site to the lowest possible level,
  • According to contracts of contractors, if subcontractors use subcontractors ‘construction qualities, construction speeds and productivity by controlling the responsible job to get the desired quality of responsible contractors’
  • Especially, it is aimed to provide all kinds of mix designs in ready mixed concrete and to provide casting of desired quality and amount of concrete, to control the purchasing and test results of samples, to protect concrete (watering, additive material, etc.) according to the properties after casting (hot, cold, frost) ensure,
  • After having done all kinds of tests about concrete steel, it is necessary to lay it in accordance with the project and to ensure that damaged reinforcing bars are removed from the site.